[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1263360":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1263360,848,1,"单选题","盖挖逆作法的施工顺序( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","构筑围护结构之地下连续墙和结构中间桩柱→回填顶板以上土方→开挖施工结构顶板→往上施工地上建筑",false,{"key":16,"text":17,"correct":14},"B","开挖施工结构顶板→回填顶板以上土方-构筑围护结构之地下连续墙和结构中间桩柱→往上施工地上建筑",{"key":19,"text":20,"correct":21},"C","构筑围护结构之地下连续墙和结构中间桩柱→开挖施工结构顶板→回填顶板以上土方→往上施工地上建筑",true,{"key":23,"text":24,"correct":14},"D","开挖施工结构顶板→构筑围护结构之地下连续墙和结构中间桩柱→回填顶板以上土方→往上施工地上建筑","",{"id":6,"name":27,"category":28,"favorite":7},"市政方向-通用基础","建筑工程"]