[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1263359":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1263359,848,1,"单选题","双侧壁导坑法施工顺序是( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","开挖上部核心土→开挖下台阶→施作内层衬砌→开挖→侧导坑→开挖另→侧导坑→拆除导坑临空部分的支护",false,{"key":16,"text":17,"correct":14},"B","开挖→侧导坑→开挖另→侧导坑→施作内层衬砌→开挖上部核心土→开挖下台阶→拆除导坑临空部分的支护",{"key":19,"text":20,"correct":14},"C","开挖上部核心土→开挖下台阶→开挖→侧导坑→开挖另→侧导坑→拆除导坑临空部分的支护→施作内层衬砌",{"key":22,"text":23,"correct":24},"D","开挖→侧导坑→开挖另→侧导坑-开挖上部核心土→开挖下台阶→拆除导坑临空部分的支护→施作内层衬砌",true,"",{"id":6,"name":27,"category":28,"favorite":7},"市政方向-通用基础","建筑工程"]