[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1263358":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1263358,848,1,"单选题","管棚超前支护技术施工工艺流程为( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","测放孔位→钻机就位→水平钻孔→压入钢管→移机→开挖→注浆→封口",false,{"key":16,"text":17,"correct":14},"B","钻机就位→测放孔位→水平钻孔→压入钢管→移机→开挖→注浆→封口",{"key":19,"text":20,"correct":21},"C","测放孔位→钻机就位→水平钻孔→压入钢管→移机→注浆→封口→开挖",true,{"key":23,"text":24,"correct":14},"D","钻机就位→测放孔位→水平钻孔→压入钢管→移机→注浆→封口→开挖","",{"id":6,"name":27,"category":28,"favorite":7},"市政方向-通用基础","建筑工程"]