[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1263351":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1263351,848,1,"单选题","GCL垫施工流程为( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","基底检验→吊运就位→人工铺展→搭接宽度调整→搭接处撒膨润土粉→进行后续施工",true,{"key":16,"text":17,"correct":18},"B","基底检验→人工铺展→吊运就位→搭接宽度调整→搭接处撒膨润土粉→进行后续施工",false,{"key":20,"text":21,"correct":18},"C","基底检验→吊运就位→搭接宽度调整→人工铺展→搭接处撒膨润土粉→进行后续施工",{"key":23,"text":24,"correct":18},"D","基底检验→吊运就位→人工铺展→搭接处撒膨润土粉→搭接宽度调整→进行后续施工","",{"id":6,"name":27,"category":28,"favorite":7},"市政方向-通用基础","建筑工程"]