[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1263250":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1263250,848,1,"单选题","劳动消耗定额又称( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","人工消耗定额",true,{"key":16,"text":17,"correct":18},"B","材料消耗定额",false,{"key":20,"text":21,"correct":18},"C","机械台班消耗定额",{"key":23,"text":24,"correct":18},"D","施工定额","",{"id":6,"name":27,"category":28,"favorite":7},"市政方向-通用基础","建筑工程"]