[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"lib-847-3":3},{"library":4,"page":9,"limit":10,"total":11,"questions":12,"related":589},{"id":5,"name":6,"category":7,"favorite":8},847,"市政方向-岗位技能","建筑工程",0,3,50,399,[13,34,42,54,66,78,90,102,114,126,138,150,162,174,183,195,207,219,231,243,255,267,279,291,303,312,324,334,343,355,364,373,383,395,407,419,429,441,451,463,475,486,496,508,520,530,542,554,566,577],{"id":14,"libraryId":5,"type":15,"typeLabel":16,"stem":17,"options":18,"answer":27,"analysis":33},1262883,1,"单选题","对于暗挖与现浇施工管道,盾构掘进每( )环为一个验收批。",[19,23,26,30],{"key":20,"text":21,"correct":22},"A","50",false,{"key":24,"text":25,"correct":22},"B","80",{"key":27,"text":28,"correct":29},"C","100",true,{"key":31,"text":32,"correct":22},"D","200","",{"id":35,"libraryId":5,"type":15,"typeLabel":16,"stem":36,"options":37,"answer":27,"analysis":33},1262884,"对于暗挖与现浇施工管道,顶管每顶进( )m为一个验收批。",[38,39,40,41],{"key":20,"text":21,"correct":22},{"key":24,"text":25,"correct":22},{"key":27,"text":28,"correct":29},{"key":31,"text":32,"correct":22},{"id":43,"libraryId":5,"type":15,"typeLabel":16,"stem":44,"options":45,"answer":24,"analysis":33},1262885,"以下说法错误的是( )。",[46,48,50,52],{"key":20,"text":47,"correct":22},"进场的水泥应按要求进行强度和安定性的复验",{"key":24,"text":49,"correct":29},"预应力钢筋超张拉的目的是为了加速钢筋松弛的早发展,减少钢筋松弛的应力损失",{"key":27,"text":51,"correct":22},"冷拉钢筋,一定要先对焊后冷拉",{"key":31,"text":53,"correct":22},"蜂窝、麻面、渗水等都与工艺操作有关",{"id":55,"libraryId":5,"type":15,"typeLabel":16,"stem":56,"options":57,"answer":31,"analysis":33},1262887,"下列不属于物理力学性能检验的是( )。",[58,60,62,64],{"key":20,"text":59,"correct":22},"抗拉强度",{"key":24,"text":61,"correct":22},"含水量",{"key":27,"text":63,"correct":22},"安定性",{"key":31,"text":65,"correct":29},"抗腐蚀性",{"id":67,"libraryId":5,"type":15,"typeLabel":16,"stem":68,"options":69,"answer":31,"analysis":33},1262888,"现场质量检查内容不包括( )。",[70,72,74,76],{"key":20,"text":71,"correct":22},"开工前检查",{"key":24,"text":73,"correct":22},"验收批和分项工程交接检查",{"key":27,"text":75,"correct":22},"隐蔽工程检查",{"key":31,"text":77,"correct":29},"已完工程检查",{"id":79,"libraryId":5,"type":15,"typeLabel":16,"stem":80,"options":81,"answer":20,"analysis":33},1262889,"施工质量控制的目标是( )。",[82,84,86,88],{"key":20,"text":83,"correct":29},"确保各工程项目质量合格",{"key":24,"text":85,"correct":22},"坚持质量标准",{"key":27,"text":87,"correct":22},"对验收批和质量控制点的控制",{"key":31,"text":89,"correct":22},"按施工合同的约定完成施工任务",{"id":91,"libraryId":5,"type":15,"typeLabel":16,"stem":92,"options":93,"answer":31,"analysis":33},1262890,"下列选项中,不属于施工过程质量控制的主要工作的是( )。",[94,96,98,100],{"key":20,"text":95,"correct":22},"验收批的自检、互检",{"key":24,"text":97,"correct":22},"监理工程师的旁站检查和验收",{"key":27,"text":99,"correct":22},"隐蔽工程验收",{"key":31,"text":101,"correct":29},"准备竣工验收资料",{"id":103,"libraryId":5,"type":15,"typeLabel":16,"stem":104,"options":105,"answer":31,"analysis":33},1262891,"正式施工前进行的事前主动质量控制的内容不包括( )。",[106,108,110,112],{"key":20,"text":107,"correct":22},"技术准备",{"key":24,"text":109,"correct":22},"施工现场准备",{"key":27,"text":111,"correct":22},"物资准备",{"key":31,"text":113,"correct":29},"人员准备",{"id":115,"libraryId":5,"type":15,"typeLabel":16,"stem":116,"options":117,"answer":31,"analysis":33},1262892,"环境条件是指对工程质量特性起重要作用的环境因素,以下不属于环境条件的是( )。",[118,120,122,124],{"key":20,"text":119,"correct":22},"施工现场自然环境因素",{"key":24,"text":121,"correct":22},"施工质量管理环境因素",{"key":27,"text":123,"correct":22},"施工作业环境因素",{"key":31,"text":125,"correct":29},"施工安全管理因素",{"id":127,"libraryId":5,"type":15,"typeLabel":16,"stem":128,"options":129,"answer":31,"analysis":33},1262893,"市政工程作为一种特殊的产品,有一些自己的特点,下列不属于其特点的是( )。",[130,132,134,136],{"key":20,"text":131,"correct":22},"适用性",{"key":24,"text":133,"correct":22},"耐久性",{"key":27,"text":135,"correct":22},"安全性",{"key":31,"text":137,"correct":29},"结构性",{"id":139,"libraryId":5,"type":15,"typeLabel":16,"stem":140,"options":141,"answer":31,"analysis":33},1262894,"下列不属于对比实际进度与计划进度常用的方法的是( )。",[142,144,146,148],{"key":20,"text":143,"correct":22},"横道图比较法",{"key":24,"text":145,"correct":22},"S形曲线比较法",{"key":27,"text":147,"correct":22},"“香蕉”形曲线比较法",{"key":31,"text":149,"correct":29},"网络图比较法",{"id":151,"libraryId":5,"type":15,"typeLabel":16,"stem":152,"options":153,"answer":24,"analysis":33},1262895,"施工进度计划跟踪与检查内容的主要工作不包括( )。",[154,156,158,160],{"key":20,"text":155,"correct":22},"跟踪检查实际施工进度",{"key":24,"text":157,"correct":29},"收集施工资料",{"key":27,"text":159,"correct":22},"整理统计检查数据",{"key":31,"text":161,"correct":22},"对比实际进度与计划进度",{"id":163,"libraryId":5,"type":15,"typeLabel":16,"stem":164,"options":165,"answer":31,"analysis":33},1262896,"某道路路堤填筑采用机械施工,需要76个台班完成,现建设单位要求7d完成,所需挖土机台数为( )台。",[166,168,170,172],{"key":20,"text":167,"correct":22},"6",{"key":24,"text":169,"correct":22},"8",{"key":27,"text":171,"correct":22},"10",{"key":31,"text":173,"correct":29},"11",{"id":175,"libraryId":5,"type":15,"typeLabel":16,"stem":176,"options":177,"answer":24,"analysis":33},1262897,"某道路工程安装砌路缘石,需要总劳动量240工日,一班制工作,每天安排作业人员为30人,则施工持续时间为( )d。",[178,179,180,181],{"key":20,"text":167,"correct":22},{"key":24,"text":169,"correct":29},{"key":27,"text":171,"correct":22},{"key":31,"text":182,"correct":22},"12",{"id":184,"libraryId":5,"type":15,"typeLabel":16,"stem":185,"options":186,"answer":27,"analysis":33},1262898,"已知某桥梁承台基坑的土方开挖量为4029m³,采用人工挖土,每工日产量定额为6.5m³,则完成基坑开挖所需的劳动量为( )工日。",[187,189,191,193],{"key":20,"text":188,"correct":22},"580",{"key":24,"text":190,"correct":22},"600",{"key":27,"text":192,"correct":29},"620",{"key":31,"text":194,"correct":22},"640",{"id":196,"libraryId":5,"type":15,"typeLabel":16,"stem":197,"options":198,"answer":27,"analysis":33},1262899,"确定劳动量和机械台班量不包括( )。",[199,201,203,205],{"key":20,"text":200,"correct":22},"工程量",{"key":24,"text":202,"correct":22},"施工方法",{"key":27,"text":204,"correct":29},"预算定额",{"key":31,"text":206,"correct":22},"施工定额",{"id":208,"libraryId":5,"type":15,"typeLabel":16,"stem":209,"options":210,"answer":31,"analysis":33},1262900,"下列关于工程量计算时应注意的问题的说法错误的是( )。",[211,213,215,217],{"key":20,"text":212,"correct":22},"分部分项工程工程量的计算单位应与相应定额标准的计算单位相一致",{"key":24,"text":214,"correct":22},"工程量的计算应结合施工方法和安全技术要求",{"key":27,"text":216,"correct":22},"按分区、分项等计算工程量",{"key":31,"text":218,"correct":29},"工程量的计算应按从易到难的顺序排列",{"id":220,"libraryId":5,"type":15,"typeLabel":16,"stem":221,"options":222,"answer":27,"analysis":33},1262901,"下列关于确定施工阶段时应注意的问题的说法错误的是( )。",[223,225,227,229],{"key":20,"text":224,"correct":22},"施工阶段的划分应与施工方法相一致",{"key":24,"text":226,"correct":22},"施工阶段划分的粗细程度主要根据单位工程施工进度计划所起的客观作用",{"key":27,"text":228,"correct":29},"适当简化施工进度计划内容,突出重点,施工过程划分应尽量细",{"key":31,"text":230,"correct":22},"所有施工阶段应大致按照施工顺序先后排列",{"id":232,"libraryId":5,"type":15,"typeLabel":16,"stem":233,"options":234,"answer":24,"analysis":33},1262902,"施工进度计划的编制依据不包括( )。",[235,237,239,241],{"key":20,"text":236,"correct":22},"工程的施工图纸",{"key":24,"text":238,"correct":29},"施工合同文件",{"key":27,"text":240,"correct":22},"工程项目施工总进度计划",{"key":31,"text":242,"correct":22},"施工方案",{"id":244,"libraryId":5,"type":15,"typeLabel":16,"stem":245,"options":246,"answer":31,"analysis":33},1262903,"单位工程施工进度计划的作用不包括( )。",[247,249,251,253],{"key":20,"text":248,"correct":22},"控制单位工程的施工进度",{"key":24,"text":250,"correct":22},"确定单位工程的各个施工过程的施工顺序",{"key":27,"text":252,"correct":22},"为编制年度等计划生产作业计划提供依据",{"key":31,"text":254,"correct":29},"控制不同时段的工程成本",{"id":256,"libraryId":5,"type":15,"typeLabel":16,"stem":257,"options":258,"answer":20,"analysis":33},1262904,"标准管理工作由( )主持。",[259,261,263,265],{"key":20,"text":260,"correct":29},"项目技术负责人",{"key":24,"text":262,"correct":22},"项目经理",{"key":27,"text":264,"correct":22},"总监理工程师",{"key":31,"text":266,"correct":22},"项目资料员",{"id":268,"libraryId":5,"type":15,"typeLabel":16,"stem":269,"options":270,"answer":24,"analysis":33},1262905,"凡已履行验收批、分项工程验收程序的,除非( )有明确要求者,一般不再进行隐蔽工程验收。",[271,273,275,277],{"key":20,"text":272,"correct":22},"建设单位",{"key":24,"text":274,"correct":29},"监理单位",{"key":27,"text":276,"correct":22},"施工总承包单位",{"key":31,"text":278,"correct":22},"市政工程管理单位",{"id":280,"libraryId":5,"type":15,"typeLabel":16,"stem":281,"options":282,"answer":31,"analysis":33},1262906,"市政工程用沥青施工检验不包括( )试验。",[283,285,287,289],{"key":20,"text":284,"correct":22},"延度",{"key":24,"text":286,"correct":22},"针人度",{"key":27,"text":288,"correct":22},"老化",{"key":31,"text":290,"correct":29},"强度",{"id":292,"libraryId":5,"type":15,"typeLabel":16,"stem":293,"options":294,"answer":27,"analysis":33},1262907,"市政工程用钢筋施工检验不包括( )。",[295,297,299,301],{"key":20,"text":296,"correct":22},"力学性能试验",{"key":24,"text":298,"correct":22},"可焊性试验",{"key":27,"text":300,"correct":29},"抗腐蚀性能试验",{"key":31,"text":302,"correct":22},"化学成分检验",{"id":304,"libraryId":5,"type":15,"typeLabel":16,"stem":305,"options":306,"answer":24,"analysis":33},1262908,"水泥物理力学性能试验不包括( )。",[307,308,309,311],{"key":20,"text":290,"correct":22},{"key":24,"text":133,"correct":29},{"key":27,"text":310,"correct":22},"凝结时间",{"key":31,"text":63,"correct":22},{"id":313,"libraryId":5,"type":15,"typeLabel":16,"stem":314,"options":315,"answer":24,"analysis":33},1262909,"( )既是保证市政工程施工质量的重要环节,又是提高市政工程安全性和耐久性的基本保证。",[316,318,320,322],{"key":20,"text":317,"correct":22},"施工测量",{"key":24,"text":319,"correct":29},"施工检验",{"key":27,"text":321,"correct":22},"施工质量检查验收",{"key":31,"text":323,"correct":22},"工程变更",{"id":325,"libraryId":5,"type":15,"typeLabel":16,"stem":326,"options":327,"answer":27,"analysis":33},1262910,"项目部应制定工程测量复核制度,实地测量必须按制度进行内部复核,并报( )复核同意后,方可进行施工。",[328,330,331,333],{"key":20,"text":329,"correct":22},"施工项目技术负责人",{"key":24,"text":262,"correct":22},{"key":27,"text":332,"correct":29},"现场监理工程师",{"key":31,"text":264,"correct":22},{"id":335,"libraryId":5,"type":15,"typeLabel":16,"stem":336,"options":337,"answer":31,"analysis":33},1262911,"( )是工程项目从施工准备到竣工验收全过程中的一项重要的技术管理工作。",[338,340,341,342],{"key":20,"text":339,"correct":22},"施工组织设计",{"key":24,"text":319,"correct":22},{"key":27,"text":321,"correct":22},{"key":31,"text":317,"correct":29},{"id":344,"libraryId":5,"type":15,"typeLabel":16,"stem":345,"options":346,"answer":31,"analysis":33},1262912,"专项方案应采用( )形式,形成书面记录。",[347,349,351,353],{"key":20,"text":348,"correct":22},"会议",{"key":24,"text":350,"correct":22},"现场讲授",{"key":27,"text":352,"correct":22},"书面",{"key":31,"text":354,"correct":29},"书面和现场讲授",{"id":356,"libraryId":5,"type":15,"typeLabel":16,"stem":357,"options":358,"answer":31,"analysis":33},1262913,"施工方案可采用( )形式,并形成书面记录。",[359,360,361,362],{"key":20,"text":348,"correct":22},{"key":24,"text":350,"correct":22},{"key":27,"text":352,"correct":22},{"key":31,"text":363,"correct":29},"会议或现场讲授",{"id":365,"libraryId":5,"type":15,"typeLabel":16,"stem":366,"options":367,"answer":20,"analysis":33},1262914,"施工组织设计交底应采用( )形式。",[368,369,370,371],{"key":20,"text":348,"correct":29},{"key":24,"text":350,"correct":22},{"key":27,"text":352,"correct":22},{"key":31,"text":372,"correct":22},"会议或书面",{"id":374,"libraryId":5,"type":15,"typeLabel":16,"stem":375,"options":376,"answer":24,"analysis":33},1262915,"危险性较大的分部分项工程专项施工方案应由( )审核签字。",[377,378,380,382],{"key":20,"text":262,"correct":22},{"key":24,"text":379,"correct":29},"施工单位技术负责人",{"key":27,"text":381,"correct":22},"企业技术负责人",{"key":31,"text":264,"correct":22},{"id":384,"libraryId":5,"type":15,"typeLabel":16,"stem":385,"options":386,"answer":27,"analysis":33},1262916,"应急预案不包括( )。",[387,389,391,393],{"key":20,"text":388,"correct":22},"应急指挥体系",{"key":24,"text":390,"correct":22},"应急准备",{"key":27,"text":392,"correct":29},"应急处理措施",{"key":31,"text":394,"correct":22},"善后处理",{"id":396,"libraryId":5,"type":15,"typeLabel":16,"stem":397,"options":398,"answer":27,"analysis":33},1262917,"下列选项中,专项施工方案内不需编制监测方案的是( )。",[399,401,403,405],{"key":20,"text":400,"correct":22},"基坑支护",{"key":24,"text":402,"correct":22},"承重支架",{"key":27,"text":404,"correct":29},"高支架模板",{"key":31,"text":406,"correct":22},"大型脚手架",{"id":408,"libraryId":5,"type":15,"typeLabel":16,"stem":409,"options":410,"answer":20,"analysis":33},1262918,"下列专业工程实行分包的,其专项方案不能由专业承包单位组织编制的是( )。",[411,413,415,417],{"key":20,"text":412,"correct":29},"高支架模板工程",{"key":24,"text":414,"correct":22},"起重机械安装拆卸工程",{"key":27,"text":416,"correct":22},"深基坑工程",{"key":31,"text":418,"correct":22},"附着式升降脚手架工程",{"id":420,"libraryId":5,"type":15,"typeLabel":16,"stem":421,"options":422,"answer":20,"analysis":33},1262919,"专项方案经审核合格,应由( )签字。",[423,425,426,427],{"key":20,"text":424,"correct":29},"技术负责人",{"key":24,"text":262,"correct":22},{"key":27,"text":264,"correct":22},{"key":31,"text":428,"correct":22},"项目监理工程师",{"id":430,"libraryId":5,"type":15,"typeLabel":16,"stem":431,"options":432,"answer":31,"analysis":33},1262920,"下列选项中,不属于施工保证措施的是( )。",[433,435,437,439],{"key":20,"text":434,"correct":22},"质量保证措施",{"key":24,"text":436,"correct":22},"安全保证措施",{"key":27,"text":438,"correct":22},"文明施工措施",{"key":31,"text":440,"correct":29},"进度保证措施",{"id":442,"libraryId":5,"type":15,"typeLabel":16,"stem":443,"options":444,"answer":27,"analysis":33},1262921,"下列分项工程中,不需要编制专项施工方案的是( )。",[445,446,447,449],{"key":20,"text":416,"correct":22},{"key":24,"text":412,"correct":22},{"key":27,"text":448,"correct":29},"脚手架工程",{"key":31,"text":450,"correct":22},"起重吊装工程",{"id":452,"libraryId":5,"type":15,"typeLabel":16,"stem":453,"options":454,"answer":27,"analysis":33},1262922,"下列选项中,施工机具和材料的选择主要考虑的因素不包括( )。",[455,457,459,461],{"key":20,"text":456,"correct":22},"应尽量选用施工单位现有机具",{"key":24,"text":458,"correct":22},"机具类型应符合施工现场的条件",{"key":27,"text":460,"correct":29},"在同一个工地上施工机具的种类和型号应尽可能多",{"key":31,"text":462,"correct":22},"考虑所选机械的运行成本是否经济",{"id":464,"libraryId":5,"type":15,"typeLabel":16,"stem":465,"options":466,"answer":20,"analysis":33},1262923,"施工材料的选择,首先应考虑( )。",[467,469,471,473],{"key":20,"text":468,"correct":29},"质量应满足设计要求",{"key":24,"text":470,"correct":22},"价格合理",{"key":27,"text":472,"correct":22},"与施工机具配合",{"key":31,"text":474,"correct":22},"运输储存成本",{"id":476,"libraryId":5,"type":15,"typeLabel":16,"stem":477,"options":478,"answer":24,"analysis":33},1262924,"( )保证施工项目顺利实施的基本条件。",[479,480,482,484],{"key":20,"text":202,"correct":22},{"key":24,"text":481,"correct":29},"施工组织",{"key":27,"text":483,"correct":22},"施工顺序",{"key":31,"text":485,"correct":22},"施工机具和材料选择供应",{"id":487,"libraryId":5,"type":15,"typeLabel":16,"stem":488,"options":489,"answer":27,"analysis":33},1262925,"( )是施工方案的核心内容,具有决定性作用。",[490,491,493,494],{"key":20,"text":483,"correct":22},{"key":24,"text":492,"correct":22},"四新技术措施",{"key":27,"text":202,"correct":29},{"key":31,"text":495,"correct":22},"质量保证方案",{"id":497,"libraryId":5,"type":15,"typeLabel":16,"stem":498,"options":499,"answer":31,"analysis":33},1262926,"下列选项中,不属于施工方案的编制原则的是( )。",[500,502,504,506],{"key":20,"text":501,"correct":22},"制订切实可行的施工方案",{"key":24,"text":503,"correct":22},"施工期限满足合同要求",{"key":27,"text":505,"correct":22},"施工费用最低",{"key":31,"text":507,"correct":29},"重点施工部位的技术创新",{"id":509,"libraryId":5,"type":15,"typeLabel":16,"stem":510,"options":511,"answer":31,"analysis":33},1262927,"制订切实可行的施工方案,首先必须从( )出发,符合现场实际情况,具有实际指导意义。",[512,514,516,518],{"key":20,"text":513,"correct":22},"工程施工成本",{"key":24,"text":515,"correct":22},"工程施工要素",{"key":27,"text":517,"correct":22},"工程施工安全",{"key":31,"text":519,"correct":29},"工程施工需求",{"id":521,"libraryId":5,"type":15,"typeLabel":16,"stem":522,"options":523,"answer":20,"analysis":33},1262928,"施工组织总设计应由( )审批。",[524,526,527,528],{"key":20,"text":525,"correct":29},"总承包单位技术负责人",{"key":24,"text":262,"correct":22},{"key":27,"text":379,"correct":22},{"key":31,"text":529,"correct":22},"项目部技术负责人",{"id":531,"libraryId":5,"type":15,"typeLabel":16,"stem":532,"options":533,"answer":27,"analysis":33},1262929,"成本计划、节能降耗等措施不包括( )。",[534,536,538,540],{"key":20,"text":535,"correct":22},"技术措施",{"key":24,"text":537,"correct":22},"组织措施",{"key":27,"text":539,"correct":29},"管理措施",{"key":31,"text":541,"correct":22},"经济措施",{"id":543,"libraryId":5,"type":15,"typeLabel":16,"stem":544,"options":545,"answer":31,"analysis":33},1262930,"文明施工和环境保护措施不包括( )。",[546,548,550,552],{"key":20,"text":547,"correct":22},"文明施工和环境保护的目标",{"key":24,"text":549,"correct":22},"文明施工和环境保护的管理网络",{"key":27,"text":551,"correct":22},"文明施工和环境保护的管理措施",{"key":31,"text":553,"correct":29},"文明施工和环境保护的资金保证措施",{"id":555,"libraryId":5,"type":15,"typeLabel":16,"stem":556,"options":557,"answer":31,"analysis":33},1262931,"施工现场准备不包括( )。",[558,560,562,564],{"key":20,"text":559,"correct":22},"办理工程开工许可等手续",{"key":24,"text":561,"correct":22},"安排好施工现场的“三通一平”",{"key":27,"text":563,"correct":22},"落实生产和生活暂设建设",{"key":31,"text":565,"correct":29},"做好施工人员的安全教育",{"id":567,"libraryId":5,"type":15,"typeLabel":16,"stem":568,"options":569,"answer":24,"analysis":33},1262932,"施工准备工作不包括( )。",[570,572,574,575],{"key":20,"text":571,"correct":22},"现场准备",{"key":24,"text":573,"correct":29},"材料准备",{"key":27,"text":107,"correct":22},{"key":31,"text":576,"correct":22},"资源准备",{"id":578,"libraryId":5,"type":15,"typeLabel":16,"stem":579,"options":580,"answer":31,"analysis":33},1262933,"主要材料需求计划是根据( )和施工进度计划编制的。",[581,583,585,587],{"key":20,"text":582,"correct":22},"施工进度计划",{"key":24,"text":584,"correct":22},"招投标文件",{"key":27,"text":586,"correct":22},"工程设计文件",{"key":31,"text":588,"correct":29},"工程项目工料分析",[590,593,596,599,602,605],{"id":15,"name":591,"category":7,"favorite":592},"领导干部任职前廉政法规知识测试题",92,{"id":594,"name":595,"category":7,"favorite":15},595,"建筑结构与设备",{"id":597,"name":598,"category":7,"favorite":15},715,"招标采购专业知识与法律法规",{"id":600,"name":601,"category":7,"favorite":15},848,"市政方向-通用基础",{"id":603,"name":604,"category":7,"favorite":8},534,"BIM工程师",{"id":606,"name":604,"category":7,"favorite":8},535]