[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1263142":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":13,"analysis":19},1263142,847,3,"判断题","当有节点工期的限制,进度计划的调整还不能满足节点工期的约束时,应考虑改变施工方案。",[11,15],{"key":12,"text":13,"correct":14},"A","正确",true,{"key":16,"text":17,"correct":18},"B","错误",false,"",{"id":6,"name":21,"category":22,"favorite":23},"市政方向-岗位技能","建筑工程",0]