[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1263046":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1263046,847,2,"多选题","在确定施工阶段时,应注意的问题包括( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","施工阶段的划分应与施工方法相一致",true,{"key":16,"text":17,"correct":18},"B","施工阶段划分的粗细程度主要根据分部分项工程施工进度计划所起的客观作用",false,{"key":20,"text":21,"correct":18},"C","适当简化施工进度计划内容,突出重点,施工过程划分应尽量细",{"key":23,"text":24,"correct":14},"D","所有施工阶段应大致按照施工顺序先后排列",{"key":26,"text":27,"correct":14},"E","施工阶段的划分一定要结合工程结构特点","ADE","",{"id":6,"name":31,"category":32,"favorite":33},"市政方向-岗位技能","建筑工程",0]