[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1263044":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1263044,847,2,"多选题","施工进度计划实施的保证措施包括( )。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","全面交底、发动群众",true,{"key":16,"text":17,"correct":14},"B","编制月作业计划",{"key":19,"text":20,"correct":14},"C","签发施工任务书",{"key":22,"text":23,"correct":14},"D","做好施工进度记录",{"key":25,"text":26,"correct":27},"E","跟踪施工进度计划的实施",false,"ABCD","",{"id":6,"name":31,"category":32,"favorite":33},"市政方向-岗位技能","建筑工程",0]