[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1263013":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1263013,847,2,"多选题","施工项目成本是指在工程项目的施工过程中所发生的全部生产费用的总和,主要由( )构成。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","直接成本",true,{"key":16,"text":17,"correct":14},"B","间接成本",{"key":19,"text":20,"correct":21},"C","规费",false,{"key":23,"text":24,"correct":14},"D","税金",{"key":26,"text":27,"correct":21},"E","总成本","ABD","",{"id":6,"name":31,"category":32,"favorite":33},"市政方向-岗位技能","建筑工程",0]