[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1262934":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1262934,847,1,"单选题","劳动力配置计划是施工现场平衡、调配劳动力的依据,是根据施工方案和( )进行编制的。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工进度计划",true,{"key":16,"text":17,"correct":18},"B","招投标文件",false,{"key":20,"text":21,"correct":18},"C","工程设计文件",{"key":23,"text":24,"correct":18},"D","工程项目工料分析","",{"id":6,"name":27,"category":28,"favorite":29},"市政方向-岗位技能","建筑工程",0]