[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1262903":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1262903,847,1,"单选题","单位工程施工进度计划的作用不包括( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","控制单位工程的施工进度",false,{"key":16,"text":17,"correct":14},"B","确定单位工程的各个施工过程的施工顺序",{"key":19,"text":20,"correct":14},"C","为编制年度等计划生产作业计划提供依据",{"key":22,"text":23,"correct":24},"D","控制不同时段的工程成本",true,"",{"id":6,"name":27,"category":28,"favorite":29},"市政方向-岗位技能","建筑工程",0]