[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1262900":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1262900,847,1,"单选题","下列关于工程量计算时应注意的问题的说法错误的是( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","分部分项工程工程量的计算单位应与相应定额标准的计算单位相一致",false,{"key":16,"text":17,"correct":14},"B","工程量的计算应结合施工方法和安全技术要求",{"key":19,"text":20,"correct":14},"C","按分区、分项等计算工程量",{"key":22,"text":23,"correct":24},"D","工程量的计算应按从易到难的顺序排列",true,"",{"id":6,"name":27,"category":28,"favorite":29},"市政方向-岗位技能","建筑工程",0]