[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1262898":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1262898,847,1,"单选题","已知某桥梁承台基坑的土方开挖量为4029m³,采用人工挖土,每工日产量定额为6.5m³,则完成基坑开挖所需的劳动量为( )工日。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","580",false,{"key":16,"text":17,"correct":14},"B","600",{"key":19,"text":20,"correct":21},"C","620",true,{"key":23,"text":24,"correct":14},"D","640","",{"id":6,"name":27,"category":28,"favorite":29},"市政方向-岗位技能","建筑工程",0]