[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1262869":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1262869,847,1,"单选题","当验收批或分项工程质量缺陷经分析评估后不能满足所定的质量标准要求,并对其他工程项目质量验收有影响时,则必须采取( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","加固处理",false,{"key":16,"text":17,"correct":18},"B","返工处理",true,{"key":20,"text":21,"correct":14},"C","限制使用",{"key":23,"text":24,"correct":14},"D","报废处理","",{"id":6,"name":27,"category":28,"favorite":29},"市政方向-岗位技能","建筑工程",0]