[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1262826":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1262826,847,1,"单选题","施工项目( )是项目部成本决策与编制计划的依据。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","成本预测",true,{"key":16,"text":17,"correct":18},"B","成本计划",false,{"key":20,"text":21,"correct":18},"C","成本实施",{"key":23,"text":24,"correct":18},"D","成本控制与调整","",{"id":6,"name":27,"category":28,"favorite":29},"市政方向-岗位技能","建筑工程",0]