[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1262481":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1262481,846,1,"单选题","实施进度计划的核心是进度计划的( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","检查措施落实情况",false,{"key":16,"text":17,"correct":18},"B","动态跟踪控制",true,{"key":20,"text":21,"correct":14},"C","分析计划执行情况",{"key":23,"text":24,"correct":14},"D","跟踪检查,收集实际数据","",{"id":6,"name":27,"category":28,"favorite":29},"设备方向-通用基础","建筑工程",0]