[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1262188":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},1262188,845,3,"判断题","案例13-1、B公司承建的某行政大楼的机电安装工程,其中通风与空调工程已进入调试阶段。空调工程要调整各房间风量、风速、温度、湿度和噪声等各项指标。由于系统多、工作量较大,防排烟工程主要在主楼有电梯的建筑部分,防排烟工程要经调试和消防功能验收,系统相对较少。由于作业队长对防排烟系统在理论上对工艺不够熟悉,尤其对诸多调节阀的功能和作用知之甚少,在进度计划实施后,指挥失当、调节效果不大,规定指标较难实现。因而作业进度缓慢,出现较大偏差,距离验收日期临近,施工员发现后进行了调整,预计不能按期完成。案例13-1这种影响进度计划实施的因素属于项目内部造成的。",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"",{"id":6,"name":21,"category":22,"favorite":23},"设备方向-岗位技能","建筑工程",0]