[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1262147":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1262147,845,2,"多选题","影响安装工程进度的因素,建设项目内部包括( )。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","土建工期的延误",true,{"key":16,"text":17,"correct":14},"B","业主资金不到位",{"key":19,"text":20,"correct":21},"C","意外事件的出现",false,{"key":23,"text":24,"correct":21},"D","施工设计图纸不能按计划或施工设计作出重大修改",{"key":26,"text":27,"correct":14},"E","各专业分包单位不能如期履行分包合同","ABE","",{"id":6,"name":31,"category":32,"favorite":33},"设备方向-岗位技能","建筑工程",0]