[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1262090":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1262090,845,2,"多选题","施工进度计划编制中应用( )方法或原则。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","循环原理",true,{"key":16,"text":17,"correct":14},"B","系统原理",{"key":19,"text":20,"correct":14},"C","动态控制原理",{"key":22,"text":23,"correct":24},"D","施工进度原理",false,{"key":26,"text":27,"correct":14},"E","信息反馈原理","ABCE","",{"id":6,"name":31,"category":32,"favorite":33},"设备方向-岗位技能","建筑工程",0]