[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1262088":3},{"question":4,"library":33},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":31,"analysis":32},1262088,845,2,"多选题","案例13-4:",[11,15,18,22,25,28],{"key":12,"text":13,"correct":14},"A","司承建的我国东南沿海某市旅游度假别墅群的机电安装工程,已处于收尾阶段,其中给水排水工程主要是室内卫生洁具的配管和每栋别墅的给水管冲洗消毒及排水管的通球试验,室外配合园林绿化做喷水池、水景等的给水管敷设。其时正值南方多雨季节,A公司项目部安排了每个月的作业计划,由于计划安排较妥善,3个月的收尾工作虽有曲折,但能如期完成。案例13-4工程在收尾阶段的给水排水安装的特点____。",true,{"key":16,"text":17,"correct":14},"B","工程比较零星分散",{"key":19,"text":20,"correct":21},"C","有室内室外两类作业环境",false,{"key":23,"text":24,"correct":21},"D","室外作业比较复杂",{"key":26,"text":27,"correct":21},"E","工程进度收室外环境影响",{"key":29,"text":30,"correct":21},"F","交代资源供给状况","AB","",{"id":6,"name":34,"category":35,"favorite":36},"设备方向-岗位技能","建筑工程",0]