[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1262087":3},{"question":4,"library":33},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":31,"analysis":32},1262087,845,2,"多选题","案例13-5:",[11,15,18,21,24,28],{"key":12,"text":13,"correct":14},"A","司承建的某医院通风与空调工程已处于试运转阶段,冷却水管道正在按计划进行用玻璃纤维瓦进行保冷。有三个作业班组平行作业与不同楼层,他们是共同完成了底层门诊大厅挂号室的冷却水保温工作而分工去各个楼层的,原因是门诊大厅的挂号室工程量大,天气渐热、人员密集流动性大,院方急于要使用,因此试运转通冷却水安排为首批。通水后发现玻璃纤维瓦浸满了凝结水,不断往外滴漏,犹如雨淋一般,究其原因,保冷瓦的内径与被保冷管外径不一致,留有空隙,致管壁结露,外敷的铝箔也不紧密,出现了如上所述的质量问题。施工员为此修正了进度计划,并进行了有关调查工作。案例13-5影响作业进度计划实施的可能有____。",true,{"key":16,"text":17,"correct":14},"B","项目内部的施工方法失误造成的返工",{"key":19,"text":20,"correct":14},"C","项目外部的影响因素",{"key":22,"text":23,"correct":14},"D","对原材进场验收把关不严",{"key":25,"text":26,"correct":27},"E","供货商供货质量发生差异",false,{"key":29,"text":30,"correct":27},"F","在施工前做好技术交底工作","ABCD","",{"id":6,"name":34,"category":35,"favorite":36},"设备方向-岗位技能","建筑工程",0]