[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1262058":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1262058,845,1,"单选题","临时用电设备在( )或设备总容量在( )者,应编制临时用电施工组织设计。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","5台及5台以上,50kW及50kW以上",true,{"key":16,"text":17,"correct":18},"B","4台及4台以上,50kW及50kW以上",false,{"key":20,"text":21,"correct":18},"C","5台及5台以上,40kW及40kW以上",{"key":23,"text":24,"correct":18},"D","6台及6台以上,50kW及50kW以上","",{"id":6,"name":27,"category":28,"favorite":29},"设备方向-岗位技能","建筑工程",0]