[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1262044":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1262044,845,1,"单选题","进度计划调整的方法不包括( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","改变作业组织形式",false,{"key":16,"text":17,"correct":14},"B","在不违反工艺规律的情况下改变专业或工序衔接关系",{"key":19,"text":20,"correct":14},"C","修正施工方案",{"key":22,"text":23,"correct":24},"D","各专业分包单位不能如期履行分包合同",true,"",{"id":6,"name":27,"category":28,"favorite":29},"设备方向-岗位技能","建筑工程",0]