[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1262006":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1262006,845,1,"单选题","项目管理层是( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","其管理以企业确定的项目成本为目标,体现现场生产成本控制中心的监理职能",false,{"key":16,"text":17,"correct":14},"B","其管理从投标开始止于结算的全过程,着眼于体现效益中心的监督职能",{"key":19,"text":20,"correct":14},"C","其管理从投标开始止于结算的全过程,着眼于体现效益中心的管理职能",{"key":22,"text":23,"correct":24},"D","其管理以企业确定的施工成本为目标,体现现场生产成本控制中心的管理职能",true,"",{"id":6,"name":27,"category":28,"favorite":29},"设备方向-岗位技能","建筑工程",0]