[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1262004":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1262004,845,1,"单选题","实际成本是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工项目承建所承包工程实际发生的各项生产费用的总和",true,{"key":16,"text":17,"correct":18},"B","指为施工准备、组织管理施工作业而发生的费用支出,这些设计施工生产必须发生的",false,{"key":20,"text":21,"correct":18},"C","指施工过程中耗费的为构成工程实体或有助于过程工程实体形成的各项费用支出的和",{"key":23,"text":24,"correct":18},"D","施工项目承建所承包工程预计发生的各项生产费用的总和","",{"id":6,"name":27,"category":28,"favorite":29},"设备方向-岗位技能","建筑工程",0]