[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1261999":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1261999,845,1,"单选题","施工成本分类的方法,按成本发生的时间划分为( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","抽象成本和实体成本",false,{"key":16,"text":17,"correct":14},"B","直接成本和间接成本",{"key":19,"text":20,"correct":21},"C","预算成本、计划成本和实际成本",true,{"key":23,"text":24,"correct":14},"D","固定成本和变动成本","",{"id":6,"name":27,"category":28,"favorite":29},"设备方向-岗位技能","建筑工程",0]