[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1261949":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1261949,845,1,"单选题","案例10-1、某公司承建的大型体育场环形地沟内冷却水循环管网,管径外径达630mm,管道除与设备法兰连接外,管与管、管与配件的连接均为沟槽式连接,应属于柔性连接。由于该公司大口径柔性连接钢管的技术尚属于初次应用,尤其对其试压会产生的弹性变形和复位情况所知不多,为此项目部编制了作业指导书,按作业指导书要求做了模拟试验,对试压用档墩和稳定支架的布置位置作出了修正,并设置了集水坑、配备潜水泵。试压作业前,项目部技术负责人组织了高层次的技术交底,要求施工员、作业队组长各司其职,实行监护,确保作业人员正确操作,增强安全防范意识。由于整个过程组织合理、方法可靠、对风险有预防,所以试压工作顺利完成,并未发生事故。案例10-1该公司技术交底考虑的内容体现了( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","技术性内容和安全防范性内容",true,{"key":16,"text":17,"correct":18},"B","经济性内容和安全防范性内容",false,{"key":20,"text":21,"correct":18},"C","技术性内容和经济防范性内容",{"key":23,"text":24,"correct":18},"D","重要性内容和安全防范性内容","",{"id":6,"name":27,"category":28,"favorite":29},"设备方向-岗位技能","建筑工程",0]