[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1261921":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1261921,845,1,"单选题","如施工中某段管子需隐蔽的,则该段管子应先进行( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","灌水试验和通球试验",true,{"key":16,"text":17,"correct":18},"B","通气试验和通球试验",false,{"key":20,"text":21,"correct":18},"C","灌水试验和通气试验",{"key":23,"text":24,"correct":18},"D","密闭试验和通球试验","",{"id":6,"name":27,"category":28,"favorite":29},"设备方向-岗位技能","建筑工程",0]