[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1261911":3},{"question":4,"library":29},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":28},1261911,845,1,"单选题","案例13-2:",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","司承建一幢高层建筑商住楼的机电安装工程,其中建筑电气工程的导管埋设和电缆桥架及线槽敷设均已到位,因而安排月度作业计划时突出了两个可平行作业的分项工程,即管内穿线和桥架内电缆敷设,由两个作业队分别进行,工作面互不干扰,人员配备相当,测量估计各要用20天方可完成。实施计划前,送检的电线质量检测报告通知,电线质量不符规定,要向供货商退货,更换合格的产品,为此B公司项目部调整了施工作业进度计划。这种影响进度计划实施的因素主要是____。",true,{"key":16,"text":17,"correct":18},"B","供应商违约,违背采购合同对产品供应质量的约定",false,{"key":20,"text":21,"correct":18},"C","施工方造成的问题",{"key":23,"text":24,"correct":18},"D","自然因素导致施工延迟",{"key":26,"text":27,"correct":18},"E","供应商与施工方没有商议好","",{"id":6,"name":30,"category":31,"favorite":32},"设备方向-岗位技能","建筑工程",0]