[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1261910":3},{"question":4,"library":29},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":28},1261910,845,1,"单选题","案例13-3:",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","司承建的某行政大楼的机电安装工程,其中通风与空调工程已进入调试阶段。空调工程要调整各房间风量、风速、温度、湿度和噪声等各项指标。由于系统多、工作量较大,防排烟工程主要在主楼有电梯的建筑部分,防排烟工程要经调试和消防功能验收,系统相对较少。调试要求各场所的风压值符合规定,风压的分布规律符合要求,项目部依据业主与公安消防机构约定的日期安排了防排烟工程调试的作业进度计划。项目部考虑其系统较少,安排专业施工员负责通风空调工程的调试,作业队长负责防排烟系统调试。由于作业队长对防排烟系统在理论上对工艺不够熟悉,尤其对诸多调节阀的功能和作用知之甚少,在进度计划实施后,指挥失当、调节效果不大,规定指标较难实现。因而作业进度缓慢,出现较大偏差,距离验收日期日益临近,施工员发现后进行了调整,预计不能按期完成。发生进度偏差的主要因素是____。",true,{"key":16,"text":17,"correct":18},"B","在项目内部,属于项目管理不当",false,{"key":20,"text":21,"correct":18},"C","作业队长不熟悉工艺要求造成的",{"key":23,"text":24,"correct":18},"D","项目外部的影响因素",{"key":26,"text":27,"correct":18},"E","供货商供货质量发生差异","",{"id":6,"name":30,"category":31,"favorite":32},"设备方向-岗位技能","建筑工程",0]