[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1261900":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1261900,845,1,"单选题","质量员发现的管道承重支架有较大的质量缺陷是处于施工高峰期,应属于( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","事前阶段的质量控制",false,{"key":16,"text":17,"correct":14},"B","事后阶段的质量控制",{"key":19,"text":20,"correct":21},"C","事中阶段的质量控制",true,{"key":23,"text":24,"correct":14},"D","施工阶段的质量控制","",{"id":6,"name":27,"category":28,"favorite":29},"设备方向-岗位技能","建筑工程",0]