[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1261899":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1261899,845,1,"单选题","施工过程发生设计更变信息传递中断而造成质量问题,应属于( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","事前质量控制失效",false,{"key":16,"text":17,"correct":18},"B","事中质量控制失效",true,{"key":20,"text":21,"correct":14},"C","事后质量控制失效",{"key":23,"text":24,"correct":14},"D","事前管理控制失效","",{"id":6,"name":27,"category":28,"favorite":29},"设备方向-岗位技能","建筑工程",0]