[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1261843":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1261843,844,1,"单选题","以下哪种方式不能作为建设工程开工日期确定的依据。（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","合同约定的开工日",false,{"key":16,"text":17,"correct":14},"B","经业主确定的开工报告中开工日期",{"key":19,"text":20,"correct":14},"C","业主下发的开工令",{"key":22,"text":23,"correct":24},"D","施工许可证中的开工日期",true,"开工日期的确定方式有以下几种：1）合同中约定具体的日期作为开工日期；2）以发包人开工通知中写明的日期作为开工日期；3）以监理人的开工通知写明日期作为开工日期；4）以承包人递交的开工报告或开工申请被批准的日期为开工日期。",{"id":6,"name":27,"category":28,"favorite":29},"(装饰施工)专业管理实务 岗位知识","建筑工程",0]