[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1261835":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1261835,844,1,"单选题","下列不属于竣工结算编制的依据有（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","施工承包合同及补充协议",false,{"key":16,"text":17,"correct":14},"B","设计施工图及竣工图",{"key":19,"text":20,"correct":14},"C","现场签证记录",{"key":22,"text":23,"correct":24},"D","未确定的甲方口头指令",true,"竣工结算编制的依据包括：1.相关法律法规2.相关工程造价计价标准、计价办法、有关规定及相关解释3.施工方承包合同、专业分包合同及补充合同，有关材料、设备采购合同4.招投标文件5.图纸、施工组织设计以及相关会议纪要5.工程预算书6.结算编制委托合同等",{"id":6,"name":27,"category":28,"favorite":29},"(装饰施工)专业管理实务 岗位知识","建筑工程",0]