[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1261818":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1261818,844,1,"单选题","下列哪一项不是施工单位难以索赔的原因。（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","对施工单位不平等的合同条款",false,{"key":16,"text":17,"correct":14},"B","建设单位不出具任何书面资料，口头要求施工",{"key":19,"text":20,"correct":21},"C","施工单位自身管理混乱",true,{"key":23,"text":24,"correct":14},"D","政府部门的强制性措施","施工单位难以索赔的原因包括：1.对施工单位不平等的合同条款2.建设单位不出具任何书面资料，口头要求施工3.政府部门的强制性措施等。",{"id":6,"name":27,"category":28,"favorite":29},"(装饰施工)专业管理实务 岗位知识","建筑工程",0]