[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1261810":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1261810,844,1,"单选题","下列哪一项资料不是项目开工前应具备的证据资料。（ ）",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","开工报告",false,{"key":16,"text":17,"correct":14},"B","施工进度计划",{"key":19,"text":20,"correct":14},"C","施工许可证",{"key":22,"text":23,"correct":24},"D","隐蔽验收记录",true,"项目开工前应具备的证据资料：开工报告、施工进度计划、施工许可证。隐蔽验收记录属于验收结果，不属于开工前具备。",{"id":6,"name":27,"category":28,"favorite":29},"(装饰施工)专业管理实务 岗位知识","建筑工程",0]