[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1261799":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1261799,844,1,"单选题","下列哪一项不属于建设单位施工合同履约的风险。（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","建设单位不按约定支付工程款",false,{"key":16,"text":17,"correct":14},"B","材料供应迟延",{"key":19,"text":20,"correct":14},"C","建设单位应协调的分包单位完成时间迟延",{"key":22,"text":23,"correct":24},"D","现场施工质量违反合同约定标准",true,"施工合同履约的风险包括：1.建设单位不按约定支付工程款2.材料供应迟延3.建设单位应协调的分包单位完成时间迟延。",{"id":6,"name":27,"category":28,"favorite":29},"(装饰施工)专业管理实务 岗位知识","建筑工程",0]