[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1261790":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1261790,844,2,"多选题","下列属于影响工期的主要因素有（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","资金因素",true,{"key":16,"text":17,"correct":14},"B","社会因素",{"key":19,"text":20,"correct":14},"C","管理因素",{"key":22,"text":23,"correct":14},"D","自然环境因素",{"key":25,"text":26,"correct":27},"E","质量因素",false,"ABCD","影响工期的主要因素包括：资金因素、社会因素、管理因素、自然环境因素。",{"id":6,"name":31,"category":32,"favorite":33},"(装饰施工)专业管理实务 岗位知识","建筑工程",0]