[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1261784":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1261784,844,2,"多选题","施工单位提出工期索赔的目的为（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","实现项目的盈利",false,{"key":16,"text":17,"correct":18},"B","免去或推卸工期延长的合同责任，规避工期罚款",true,{"key":20,"text":21,"correct":18},"C","因工期延长而造成的费用索赔",{"key":23,"text":24,"correct":14},"D","延长工期",{"key":26,"text":27,"correct":14},"E","加速施工，确保工期内完成施工","BC","工期索赔的目的为免去或推卸工期延长的合同责任，规避工期罚款以及索赔因工期延长而造成的费用。",{"id":6,"name":31,"category":32,"favorite":33},"(装饰施工)专业管理实务 岗位知识","建筑工程",0]