[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1261693":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1261693,844,1,"单选题","下列不属于工程量索赔的必要条件的有（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","建设单位不同意签证或不完全签证",false,{"key":16,"text":17,"correct":14},"B","在合同约定期限内提出",{"key":19,"text":20,"correct":14},"C","证据事实确凿、充分",{"key":22,"text":23,"correct":24},"D","应有相应的单价及总价",true,"工程量索赔的必要条件的有：1.建设单位不同意签证或不完全签证2.在合同约定期限内提出3.证据事实确凿、充分。",{"id":6,"name":27,"category":28,"favorite":29},"(装饰施工)专业管理实务 岗位知识","建筑工程",0]