[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1261692":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1261692,844,1,"单选题","下列哪项不属于施工单位可主张工期顺延的理由。（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","发包人未按约支付工程款",false,{"key":16,"text":17,"correct":14},"B","不可抗力",{"key":19,"text":20,"correct":14},"C","发包人未按约提供协助工作",{"key":22,"text":23,"correct":24},"D","施工单位的供应商未按期供应材料",true,"施工单位的供应商未按期供应材料属于施工单位的原因，依照合同和有关标准规定不得进行工期索赔。",{"id":6,"name":27,"category":28,"favorite":29},"(装饰施工)专业管理实务 岗位知识","建筑工程",0]