[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1261679":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1261679,844,1,"单选题","下列哪一项不属于建筑施工企业可以顺延工程工期，并有权要求赔偿停工、窝工等损失的理由。（ ）",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","发包方未按照约定的时间和要求提供原材料",false,{"key":16,"text":17,"correct":14},"B","发包方未按约定提供设备",{"key":19,"text":20,"correct":14},"C","发包方或总包单位未按时提供场地",{"key":22,"text":23,"correct":24},"D","发包方未按约定提供施工许可证",true,"发包方未按约定提供施工许可证不能开工，已经违反法律及有关规定。",{"id":6,"name":27,"category":28,"favorite":29},"(装饰施工)专业管理实务 岗位知识","建筑工程",0]