[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1261674":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1261674,844,1,"单选题","专项方案实施前，编制人员或项目技术负责人应当向现场管理人员和作业人员进行（ ）交底。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","安全技术",true,{"key":16,"text":17,"correct":18},"B","图纸",false,{"key":20,"text":21,"correct":18},"C","施工组织设计",{"key":23,"text":24,"correct":18},"D","分项工程技术","专项方案实施前，编制人员或项目技术负责人应当向现场管理人员和作业人员进行安全技术交底。",{"id":6,"name":27,"category":28,"favorite":29},"(装饰施工)专业管理实务 岗位知识","建筑工程",0]