[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1261580":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1261580,844,2,"多选题","施工准备阶段现场准备的安全技术措施包括（ ）的内容。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","按施工总平面图要求做好现场施工准备",true,{"key":16,"text":17,"correct":14},"B","电器线路，配电设备符合安全要求，有安全用电防护措施",{"key":19,"text":20,"correct":14},"C","场内道路畅通，设交通标志，危险地带设危险信号及禁止通行标志",{"key":22,"text":23,"correct":14},"D","保证特殊工种使用工具、器械质量合格，技术性能良好",{"key":25,"text":26,"correct":27},"E","现场定期检查",false,"ABCD","施工准备阶段现场准备的安全技术措施包括按施工总平面图要求做好现场施工准备；电器线路，配电设备符合安全要求，有安全用电防护措施；场内道路畅通，设交通标志，危险地带设危险信号及禁止通行标志；保证特殊工种使用工具、器械质量合格，技术性能良好",{"id":6,"name":31,"category":32,"favorite":33},"(装饰施工)专业管理实务 岗位知识","建筑工程",0]