[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1261543":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1261543,844,1,"单选题","横杆长度大于（ ）时，必须加设栏杆柱，栏杆柱的固定及其与横杆的连接，其整体构造应在任何一处能经受任何方向的1000N的外力。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","1m",false,{"key":16,"text":17,"correct":18},"B","2m",true,{"key":20,"text":21,"correct":14},"C","2.5m",{"key":23,"text":24,"correct":14},"D","3m","根据《建设工程安全生产管理条例》，横杆长度大于2m时，必须加设栏杆柱，栏杆柱的固定及其与横杆的连接，其整体构造应在任何一处能经受任何方向的1000N的外力。",{"id":6,"name":27,"category":28,"favorite":29},"(装饰施工)专业管理实务 岗位知识","建筑工程",0]