[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1261522":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1261522,844,2,"多选题","抹灰工程施工过程中，为解决出现空鼓、开裂的质量问题，采取的措施有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","砂子采用平均粒径35mm以下的细砂",false,{"key":16,"text":17,"correct":18},"B","施工前进行基体的清理和浇水",true,{"key":20,"text":21,"correct":14},"C","使用不同品种的水泥混用",{"key":23,"text":24,"correct":18},"D","施工操作时分层分遍认真压实",{"key":26,"text":27,"correct":18},"E","施工后及时浇水养护","BDE","抹灰工程施工过程中，为解决出现空鼓、开裂的质量问题，采取的措施有施工前进行基体的清理和浇水、施工操作时分层分遍认真压实和施工后及时浇水养护。",{"id":6,"name":31,"category":32,"favorite":33},"(装饰施工)专业管理实务 岗位知识","建筑工程",0]