[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1261505":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1261505,844,2,"多选题","下列选项中，属于建筑安装工程中措施项目费组成内容的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","工程排污费",false,{"key":16,"text":17,"correct":18},"B","夜间施工增加费",true,{"key":20,"text":21,"correct":14},"C","施工机械使用费",{"key":23,"text":24,"correct":18},"D","二次搬运费",{"key":26,"text":27,"correct":18},"E","安全施工费","BDE","根据《建设工程工程量清单计价规范》GB50500一2013有关规定，建筑安装工程中措施项目费包括大型机械设备进出场及安拆费、冬雨季施工增加费、夜间施工增加费、安全文明施工费、特殊地区施工增加费、脚手架工程费、已完工程及设备保护费、工程定位复测费",{"id":6,"name":31,"category":32,"favorite":33},"(装饰施工)专业管理实务 岗位知识","建筑工程",0]