[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1261492":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1261492,844,2,"多选题","关于金属网计量的说法，正确的有（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","包括油漆",true,{"key":16,"text":17,"correct":14},"B","包括制作",{"key":19,"text":20,"correct":14},"C","包括安装",{"key":22,"text":23,"correct":14},"D","包括运输",{"key":25,"text":26,"correct":27},"E","以重量计算",false,"ABCD","根据《建设工程工程量清单计价规范》GB50500一2013有关规定，金属网计量的说法，包括油漆、包括制作、包括安装和包括运输；楼地面隔热铺贴计算时不扣除柱、垛所占体积",{"id":6,"name":31,"category":32,"favorite":33},"(装饰施工)专业管理实务 岗位知识","建筑工程",0]