[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1261489":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},1261489,844,3,"判断题","根据工程量清单计价规则，一台机械工作24小时为一个台班。",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"根据工程量清单计价规则，一台机械工作8小时为一个台班。",{"id":6,"name":21,"category":22,"favorite":23},"(装饰施工)专业管理实务 岗位知识","建筑工程",0]